Question 1
A project manager for an iterative project noticed that retrospective items indicate that the team is not fully conversant with the principles of iterative development. The team meets to analyze the gaps in the training that recently concluded with a third-party trainer.
What should the project manager do next?
What should the project manager do next?
Question 2
During the implementation of a project the project team discovered a new opportunity After an internal review the project team agreed that the opportunity is outside of the project scope The project manager decided to update the risk register and escalate the opportunity to a higher level What should the project manager do next with this opportunity?
Question 3
The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:
Question 4
A project manager is leading a project which shows a trend to exceed the cost baseline.
What should the project manager do first to manage the budget?
What should the project manager do first to manage the budget?
Question 5
The project governance approach should be described in the: