Question 26
Which is created during the Starting up a Project process?
Question 27
Which is a benefit of using PRINCE2?
Question 28
Whose approval is needed to replace a Stage Plan with an Exception Plan?
Question 29
Identify the missing words in the following sentence.
At an agreed frequency, a Team Manager will send a [ ? ] to the Project Manager.
At an agreed frequency, a Team Manager will send a [ ? ] to the Project Manager.
Question 30
According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?