Question 1
Which two statements are key responsibilities of supplier representative?
1. They highlight areas that the project may impact from a technical perspective.
2. They are partially assigned to the delivery team.
3. They create the project's specialist products.
4. They prioritize requirements.
1. They highlight areas that the project may impact from a technical perspective.
2. They are partially assigned to the delivery team.
3. They create the project's specialist products.
4. They prioritize requirements.
Question 2
Which statement about the 'keep teams stable' target is CORRECT?
Question 3
What is the definition of a timebox?
Question 4
How is the 'tailor to suit the project' principle applied in an agile context?
Question 5
Which statement describes the Kanban approach?