Which role is part of the project management team?
Correct Answer: D
Question 122
Which is the purpose of the Change theme?
Correct Answer: B
The purpose of the Change theme in PRINCE2 is to establish a clear, structured approach for identifying, assessing, and controlling changes to baselined products. This theme ensures that only approved changes are implemented, helping to manage and minimize their potential impacts on the project's objectives. References: PRINCE2 Foundation manual, PRINCE2 official resources