Question 36
What does the communication management approach define?
1. How versions of products will be described on information sent to interested parties
2. How information should be sent to interested parties
3. How often information should be sent to interested parties
4. How the PRINCE2 roles will be combined during the project
1. How versions of products will be described on information sent to interested parties
2. How information should be sent to interested parties
3. How often information should be sent to interested parties
4. How the PRINCE2 roles will be combined during the project
Question 37
What action is taken as part of the 'controlling a stage' process?
1. Create an exception plan
2. Authorize work to be done
3. Take corrective action
4. Obtain approvals for completed products
1. Create an exception plan
2. Authorize work to be done
3. Take corrective action
4. Obtain approvals for completed products
Question 38
Which should be funded from a change budget?
Question 39
When considering risks, which describes an opportunity in a project?
Question 40
Which is a purpose of the business case theme?