Question 51

Although it is not specified in the current corporate branding standards, the MFH corporate logo should be shown on the front page of the service level agreement.
  • Question 52

    Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.
    The Stage Plan for stage 3 has been produced.
    The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.
    None of the £500 change budget has been used to date and this is available for the stage.
    Which 2 statements apply to the Budgets section?
  • Question 53

    Which statement is an appropriate entry for the project approach heading within the Project Brief?
  • Question 54

    Based on lessons from previous projects that used the ABC Company standard development model, the
    project board has set low cost and time tolerances for stage 2. As a result, the project manager plans to set
    very low tolerances for time and cost for all work packages to be carried out during stage 2.
    Is this an appropriate application of the 'manage by exception' principle, and why?
  • Question 55

    There is no mention of any Stage Plans, yet there are two further stages proposed. How will this be resolved?