Question 61

The project is at the start of stage 3, and there will be six teams working on product delivery. In order to exercise control, the project manager has asked each team to submit a detailed team plan for approval. The external team manager for the 'e-learning course' has agreed to submit a summary to the project manager, but will submit the detailed team plan to the senior supplier to review and approve.
Is the team manager's response appropriate, and why?
  • Question 62

    It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely.
    There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.
    Which product should show that without the calendar the company is going to experience difficulties recovering its decline in orders, and alternative solutions are required if the company is going to recover its position?
  • Question 63

    Who sets the tolerances for a work package?
  • Question 64

    Which statement applies to the Introduction section?
  • Question 65

    The project is at the start of stage 3, and there will be six teams working on product delivery. In order to exercise control, the project manager has asked each team to submit a detailed team plan for approval. The external team manager for the 'e-learning course' has agreed to submit a summary to the project manager, but will submit the detailed team plan to the senior supplier to review and approve.
    Is the team manager's response appropriate, and why?
  • Premium Bundle

    Newest PRINCE2-Practitioner Exam PDF Dumps shared by BraindumpsPass.com for Helping Passing PRINCE2-Practitioner Exam! BraindumpsPass.com now offer the updated PRINCE2-Practitioner exam dumps, the BraindumpsPass.com PRINCE2-Practitioner exam questions have been updated and answers have been corrected get the latest BraindumpsPass.com PRINCE2-Practitioner pdf dumps with Exam Engine here:

    (285 Q&As Dumps, 40%OFF Special Discount: Exam-Tests)
    Other Version
    1087PRINCE2.PRINCE2-Practitioner.v2024-03-28.q141
    3699PRINCE2.PRINCE2-Practitioner.v2022-06-08.q175
    4334PRINCE2.PRINCE2-Practitioner.v2022-01-15.q133
    Latest Upload
    117Oracle.1Z0-1057-23.v2025-09-10.q47
    150Google.Professional-Cloud-Network-Engineer.v2025-09-09.q179
    131SAP.C-S4EWM-2023.v2025-09-08.q83
    162TheSecOpsGroup.CNSP.v2025-09-08.q20
    220CFAInstitute.ESG-Investing.v2025-09-08.q173
    155PECB.ISO-IEC-27001-Lead-Implementer.v2025-09-06.q132
    145Salesforce.Data-Architect.v2025-09-05.q216
    139Adobe.AD0-E605.v2025-09-05.q50
    183Nutanix.NCP-MCI-6.10.v2025-09-05.q55
    114Oracle.1z0-591.v2025-09-05.q104