Question 106
Which statement applies to the Introduction section?
Question 107
According to PRINCE2, which statement about appointing the MFH Quality Manager to administer the
configuration management procedure is correct?
configuration management procedure is correct?
Question 108
Scenario:
Techniques, processes and procedures
1. Any threat that may result in a loss of MFH data must be escalated immediately.
Joint agreements
2.Work is to start at the beginning of week 2 (Stage 4).
3.The project will take two years to complete, at an estimated cost of (GBP)2.5m. Tolerances
4.None.
Constraints
5.MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.
6.Installation work must take place during MFH normal working hours.
7.+(GBP)10,000 / -(GBP)25,000.
Reporting arrangements
8.Highlight Report every Monday by 10.00 am.
9.The report must contain a summary of all products worked on during the previous week.
10.
Project Manager must be notified of any issues immediately by telephone.
Problem handling and escalation
11. Impact analysis of all issues must be completed within 24 hours.
Extracts or references
12. The Stage Plan for stage 4 is available from Project Support.
Approval method
13. Project Assurance will review the completed Work Package and confirm completion.
Which 2 statements apply to either the Development Interfaces or Operations and maintenance interfaces sections?
Techniques, processes and procedures
1. Any threat that may result in a loss of MFH data must be escalated immediately.
Joint agreements
2.Work is to start at the beginning of week 2 (Stage 4).
3.The project will take two years to complete, at an estimated cost of (GBP)2.5m. Tolerances
4.None.
Constraints
5.MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.
6.Installation work must take place during MFH normal working hours.
7.+(GBP)10,000 / -(GBP)25,000.
Reporting arrangements
8.Highlight Report every Monday by 10.00 am.
9.The report must contain a summary of all products worked on during the previous week.
10.
Project Manager must be notified of any issues immediately by telephone.
Problem handling and escalation
11. Impact analysis of all issues must be completed within 24 hours.
Extracts or references
12. The Stage Plan for stage 4 is available from Project Support.
Approval method
13. Project Assurance will review the completed Work Package and confirm completion.
Which 2 statements apply to either the Development Interfaces or Operations and maintenance interfaces sections?
Question 109
During stage 3, the operational staff that handle course bookings asked for the project scope to be increased for an online booking function. The additional product has been as it will enable them to process bookings more quickly and accurately.
Is this an appropriate application of the 'focus on products' principle, and why?
Is this an appropriate application of the 'focus on products' principle, and why?
Question 110
Which of the following principles describes this statement?
"xxx defines tolerances for each project objective to establish limits of delegated authority"
"xxx defines tolerances for each project objective to establish limits of delegated authority"