Question 86

Scenario
Additional Information
Product Description

Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.
The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors) Introduction
1. This document defines the approach to be taken to achieve the required quality levels during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Which is a correctly defined acceptance criterion for the transferred staff?
  • Question 87

    Scenario
    A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers' performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:
    # Do nothing.
    # Re-engineer selected business functions.
    # Outsource selected business functions.
    The feasibility study concluded that there was a case for outsourcing the MFH Information Technology Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were:
    # One service provider should be contracted to provide the services currently provided by the Information Technology Division and the Facilities Division.
    # A 10-year service contract should be agreed with the selected service provider.
    The feasibility study developed high-level designs of the current organization, processes, systems and operating models, plus an outline Business Case for the required project. The external consultants also made the following recommendations for the management of the project:
    # Use PRINCE2.
    # Set up the project with 4 management stages:
    Stage 1. Standard PRINCE2 initiation activities.
    Stage 2. Create detailed designs (future organization, processes, systems and operating models) and the service level agreement between MFH and the future service provider.
    Stage 3. Request and evaluate proposals, select service provider and agree contract.
    Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run trial period.
    Initial estimates indicated that the project would cost £2.5m and take two years to complete.
    MFH senior management agreed that there was a case for outsourcing, and accepted the recommendations as a basis for the project. There is an expected saving of £20m over 10 years.
    The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage.
    Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs.
    Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

    Question 88

    Which 2 statements explain why Central Records should be appointed as Project Support for this project?
  • Question 89

    ABC Company has decided to include the Health and Safety Training Project in a programme to support their
    strategy to deliver globally. The programme team has provided the detailed business justification and, as a
    result, the project board has decided that the business case will not need refining further during the 'initiating a
    project' process.
    Is this an appropriate action for the project board, and why?
  • Question 90

    One of the senior managers of the company that is developing the 'e-learning course' has worked with ABC
    Company before. The team manager for the delivery of the 'e-learning course' has looked on ABC Company's
    intranet, but cannot find any reference to this work. The team manager has contacted the senior manager to
    discuss this project.
    Is this an appropriate application of the 'learn from experience' principle, and why?
  • Premium Bundle

    Newest PRINCE2Practitioner Exam PDF Dumps shared by BraindumpsPass.com for Helping Passing PRINCE2Practitioner Exam! BraindumpsPass.com now offer the updated PRINCE2Practitioner exam dumps, the BraindumpsPass.com PRINCE2Practitioner exam questions have been updated and answers have been corrected get the latest BraindumpsPass.com PRINCE2Practitioner pdf dumps with Exam Engine here:

    (266 Q&As Dumps, 40%OFF Special Discount: Exam-Tests)
    Latest Upload
    200PaloAltoNetworks.NGFW-Engineer.v2026-05-01.q43
    290Nokia.4A0-113.v2026-05-01.q69
    250EC-COUNCIL.312-49v11.v2026-04-30.q214
    226Microsoft.MB-820.v2026-04-30.q101
    205Salesforce.MC-202.v2026-04-30.q57
    203BICSI.INSTC_V8.v2026-04-29.q53
    332NMLS.MLO.v2026-04-28.q82
    241NCARB.Project-Management.v2026-04-28.q27
    454EMC.D-AV-DY-23.v2026-04-27.q184
    1107ServiceNow.CSA.v2026-04-27.q483