Question 36
True or False: Cycle Time is a lagging indicator.
Question 37
True or False: In Scrum, the Developers are required to conform to the Definition of Done. When adding Kanban to Scrum, they will also need to conform to their Definition of Workflow.
Question 38
True or False: The main role of WIP aging is to help identify flow bottlenecks; where work may be impeded or constrained.
Question 39
The team needs to work on a high priority urgent unplanned item, but they are at their WIP limit.
True or False: They should change the WIP limit at their Daily Scrum to enable them to pull in that item.
True or False: They should change the WIP limit at their Daily Scrum to enable them to pull in that item.
Question 40
What can a specific work item's Cycle Time metric be used for? (choose the best three answers)