Question 1

Which of the following are lagging indicator metrics?
(choose the best three answers)
  • Question 2

    True or False: In a flow-based system, the number of tasks is not necessarily limited, rather the amount of value-generating work items is limited.
  • Question 3

    Who must change the Work in Progress (WIP) Limits in the Definition of Workflow when urgent work emerges from the Sprint?
    (choose the best answer)
  • Question 4

    According to Little's Law, which of the following statements is true if a team reduces its Work in Progress (WIP) limit? (choose the best two answers)
  • Question 5

    When using Kanban in Scrum, a team needs to use which of the following four metrics of flow? (choose the best four answers)