Question 56
Every Development Team should have the competencies and skills needed to deliver a Done Increment in a Sprint.
Question 57
What should the Development Team do if they are approached by someone outside the team and asked to add a "very important" item to a Sprint that is in progress?
Question 58
Peter, the Product Owner, has been giving positive recognition to individual Development Team members who have moved their work to 'done' during the Daily Scrum. Peter wants to ensure the team is adhering to the ideal guideline on the burndown chart.
What would be two valid actions for Steven, the Scrum Master, to take? (Choose two.)
What would be two valid actions for Steven, the Scrum Master, to take? (Choose two.)
Question 59
Steven is a Scrum Master for three different teams building a single product from the same Product Backlog. Development Team members from each team have approached Steven complaining that their teams need Nicole, an external specialist, to commit full time for their next Sprint.
Which three acceptable solutions would Steven consider? (Choose three.)
Which three acceptable solutions would Steven consider? (Choose three.)
Question 60
An organization wants to apply Scrum to build a new product and has hired Steven to be the Scrum Master of three new teams that will build the first release. The organization is new to Scrum and asks Steven for advice on how to start.
Which two things should Steven first advise? (Choose two.)
Which two things should Steven first advise? (Choose two.)