Question 41

Paul, a Product Owner of one of the Scrum Teams, has been attending the Daily Scrum. During the Daily Scrum, the Development Team members have been reporting their daily work to Paul so that he is aware of their Sprint progress and what each member is working on.
What is the best action for the Scrum Master to take?
  • Question 42

    During the Sprint Review, one of the stakeholders announces that due to recent market changes, there is risk that funding might be reduced for the project. This triggers tensions to rise and arguments to break out between members.
    As a Scrum Master, what would be the best two actions to take? (Choose two.)
  • Question 43

    A Scrum Team must have a Product Owner and Scrum Master.
  • Question 44

    Steven is a Scrum Master of a Development Team that has members working in different cities and time zones. Organizing the Scrum events is time consuming and requires a lot of effort to set up and run. The Development Team proposes to only hold the Daily Scrum on Mondays.
    Which two responses would be most appropriate from Steven? (Choose two.)
  • Question 45

    What must the Development Team do during the first Sprint?