Question 41

Several Sprints into a project, a client is complaining to the Product Owner about the poor performance of the product.
As a Scrum Master, how can you help the Product Owner?
  • Question 42

    At the fifth Sprint Retrospective, the Product Owner mentions that he is surprised about the amount of technical debt that has built up in the system and that the product is not able to support an adequate number of users. Peter, the Product Owner, is upset that the product will need several more Sprints to address the scalability issues in order to meet his expectations.
    What factors may have led to this?
  • Question 43

    If burndown charts are used to visualize progress, what does a trendline through a release burndown chart indicate?
  • Question 44

    Which of the following are time-boxed events in Scrum?
  • Question 45

    During the Sprint Retrospective, the team is discussing the quality issues that prevented the team from delivering a releasable Increment at the end of the Sprint. The Development Team does, however, mention that they were able to achieve a high velocity.
    What are the best two responses for Steven, their Scrum Master, to take? (Choose two.)