Question 6
The director of engineering in your organization always stresses the importance of meeting deadlines in order for the engineering department to be seen as a reliable source for the product management department. The director has calculated that the team's velocity needs to increase an additional 15% to meet the commitment he made to management for the release date of the product.
He asks Steven, the team's Scrum Master, to increase his team's velocity. Which would be the best two responses for Steven to take? (Choose two.)
He asks Steven, the team's Scrum Master, to increase his team's velocity. Which would be the best two responses for Steven to take? (Choose two.)
Question 7
During Sprint Planning, the Definition of Done will help the Development Team forecast the amount of work, selected from the Product Backlog, deemed feasible to make 'done' by the end of the Sprint.
Which two items best describes what 'done' means? (Choose two.)
Which two items best describes what 'done' means? (Choose two.)
Question 8
A new member has just joined an existing Development Team that has been together for several Sprints. During the Sprint, the individual has been trying to share his ideas and viewpoints but is continuously ignored by the rest of the Development Team.
Which three Scrum Values has the Development Team been neglecting? (Choose three.)
Which three Scrum Values has the Development Team been neglecting? (Choose three.)
Question 9
Who must ensure that the work done for a Product Backlog item conforms to the Definition of "Done?"
Question 10
Steven is a Scrum Master of a Scrum Team that is new to Scrum. At the halfway point of the Sprint, the Product Owner comes to Steven telling him that he is concerned the Development Team will not be able to complete the entire Sprint Backlog by the end of the Sprint.
What should Steven do in this situation?
What should Steven do in this situation?