Question 81
A Scrum Team has been working on a product for several iterations and has an average velocity of 55 units of 'done' work per Sprint. A second team will be added to work on the same product.
What might be the impact on the original team?
What might be the impact on the original team?
Question 82
During a Sprint Review, the Product Owner determines that she is going to release the currer Increment to production. The stakeholders ask to stop the Sprint to react more quickly to the user feedback that is expected after this release. The Product Owner prefers to continue the Sprint to make progress with the next release.
You facilitate a discussion on how to proceed.
What are two acceptable results of this discussion?
(choose the best two answers)
You facilitate a discussion on how to proceed.
What are two acceptable results of this discussion?
(choose the best two answers)
Question 83
Using Scrum ensures that adding more resources to a project proportionally increases the value delivered.
Question 84
Steven, the Scrum Master, is approached by one of the Development Team members saying that they are not completing regression tests for all of the work they are performing to the level defined in the Definition of Done. They have discussed this with the Product Owner and decided to remove regression testing from the Definition of Done.
Which two actions are the most appropriate for Steven to take? (Choose two.)
Which two actions are the most appropriate for Steven to take? (Choose two.)
Question 85
In an environment where user acceptance testing is required before the Increment can be put into production, a development manager proposes to have user acceptance testing done every third Sprint, because the feedback from the user acceptance tests are disrupting work in Sprints. Is this a good idea? (Choose the best answer)