Question 126
According to the values of Scrum, which is the best way to create Development Teams?
Question 127
During a Sprint Review, the Product Owner determines that she is going to release thecurrentIncrement to production. The stakeholders ask to stop the Sprint to react more quickly to the user feedback that is expected after this release. The Product Owner prefers to continue the Sprint to make progress with the next release.
You facilitate a discussion on how to proceed.
What are two acceptable results of this discussion?
(choose the best two answers)
You facilitate a discussion on how to proceed.
What are two acceptable results of this discussion?
(choose the best two answers)
Question 128
An important aspect of Scrum are timeboxes. Select two ways in which timeboxing reinforces the creation of value.
(choose the best two answers)
(choose the best two answers)
Question 129
If there are multiple Scrum Teams working on the same product, all of the Scrum Teams must mutually define a Definition of Ready (DoR). The DoR is a checklist that the Product Owner must fulfill before a Product Backlog item can be presented at the Sprint Planning. This protects the Development Team from interruptions and disruptions during the Sprint.
Question 130
Which four of the following risks to product development are addressed by Scrum?
(choose the best four answers)
(choose the best four answers)