Question 11
An architect is working on a very large and complex project consisting of multiple buildings with overlapping phases.
Which tool should be used to communicate important deadlines to the team?
Which tool should be used to communicate important deadlines to the team?
Question 12
An architecture firm has a C401 agreement with their consultants for a new design-bid-build residential tower.
The architect has approved a schedule provided by the mechanical engineer that includes a two-week quality control review after each delivery milestone.
During the design development phase, the owner requests that the architect change the 8,000-square-foot business center amenity for tenants to a private restaurant. The mechanical engineer informs the architect that their schedule must be extended by four weeks to meet the owner's request.
What should the architecture firm do first to maintain the start of construction?
The architect has approved a schedule provided by the mechanical engineer that includes a two-week quality control review after each delivery milestone.
During the design development phase, the owner requests that the architect change the 8,000-square-foot business center amenity for tenants to a private restaurant. The mechanical engineer informs the architect that their schedule must be extended by four weeks to meet the owner's request.
What should the architecture firm do first to maintain the start of construction?
Question 13
A geotechnical report for a public project reveals a previously unknown condition and indicates that there is rock directly beneath the existing grade. The proposed building will now require a shallow foundation. The chosen location was the result of a three-year process evaluating multiple potential sites.
Which actions should the architect take next as a result of the geotechnical report results? Check the three that apply.
Which actions should the architect take next as a result of the geotechnical report results? Check the three that apply.
Question 14
The architect is on site to evaluate the completed work by the contractor. During the evaluation, the architect notices a structural connection that deviates from the contract documents.
According to AIA B101, to which party should the architect report this observed deviation?
According to AIA B101, to which party should the architect report this observed deviation?
Question 15
Which four factors will most affect the choice of project delivery method? Check the four that apply.