Question 21
What is the best method for an architect to reduce liability related to unknown site conditions?
Question 22
A principal architect is working with a school district on designing an 18,000-square-foot athletics training facility. During the DD phase, the principal notices that the firm's younger staff has produced equipment plans that do not coordinate with the electrical engineer's sheets.
How should the principal architect respond to the lack of coordination? Check the three that apply.
How should the principal architect respond to the lack of coordination? Check the three that apply.
Question 23
During the initial construction documents phase meeting, the owner states a strong desire to decrease the time required for the construction documents phase. The owner plans to submit the documents to the building department early for the building permit. Although the project is currently on schedule, the architect plans to comply with the owner's request.
Which action should the architect take?
Which action should the architect take?
Question 24
An architectural firm is developing construction documents (CDs) for a multi-story manufacturing facility.
The project requirements include high-volume ventilation and filtration air distribution systems and heavy floor load design to accommodate the manufacturing equipment and processes. The project manager (PM) is planning for coordination and constructability review of the project documents at 80% CDs.
What actions should the PM take to ensure an effective quality control review? Check the three that apply.
The project requirements include high-volume ventilation and filtration air distribution systems and heavy floor load design to accommodate the manufacturing equipment and processes. The project manager (PM) is planning for coordination and constructability review of the project documents at 80% CDs.
What actions should the PM take to ensure an effective quality control review? Check the three that apply.
Question 25
An architect is evaluating a change order.
Where should the costs for the project superintendent or general foreman be included?
Where should the costs for the project superintendent or general foreman be included?