Question 56
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?


Question 57
Project delays are best analyzed
Question 58
If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?
Question 59
Using the normal schedule, what is the owner's total cost of the project?
Question 60
Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?


