Question 46

Determine the correct formula and date for the late finish for Activity 2001.
  • Question 47

    Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?
  • Question 48

    You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
  • Question 49

    Why does activity 1001 have two successor activities?
  • Question 50

    Why does activity 11001 not show successor activities?