Question 1
Which of the following is used to plan basic dates manually for WBS elements? Choose the correct answers. There are 2 correct answers to this question.
Question 2
Cost & Budget
You are using network and internal activities in your project . You have already create a purchase requisition and the bid invitation., and have entered the quotation ...
What is the typical sequence for the following business transactions and document.
You are using network and internal activities in your project . You have already create a purchase requisition and the bid invitation., and have entered the quotation ...
What is the typical sequence for the following business transactions and document.
Question 3
Material
How can the system activate requirements (such as reservations or purchase requisitions)?
Note: There are 2 correct answers to this question
How can the system activate requirements (such as reservations or purchase requisitions)?
Note: There are 2 correct answers to this question
Question 4
You want to determine the planned costs for an internally processed activity. Which data do you need?
Note: There are 2 correct Answers to this question.
Note: There are 2 correct Answers to this question.
Question 5
A customer needs to analyze the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct answers to this question