Question 6

You have created an internally-processed network activity, and assigned a work center and the work.
After saving, you discover that no planned costs are displayed in the cost element report for the activity.
What could be the reason? Note: There are 3 correct Answers to this question.
  • Question 7

    You have created an internally-processed network activity, and assigned a work center and the work. After saving,
    you discover that no planned costs are displayed in the cost element report for the activity. What could be the reason? Note: There are 3 correct answers to this question
  • Question 8

    You are using budgeting and active availability control. How can availability control be activated? Note: There are 2 correct answers to this question
  • Question 9

    You are working with predefined project coding masks to create projects. Which of the following statements apply? Note: There are 2 correct Answers to this question.
  • Question 10

    Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct Answers to this question.