Question 156

You work as a project manager for BlueWell Inc. Your project is using a new material to construct a large warehouse in your city. This new material is cheaper than traditional building materials, but it takes some time to learn how to use the material properly. You have communicated to the project stakeholders that you will be able to save costs by using the new material, but you will need a few extra weeks to complete training to use the materials. This risk response of learning how to use the new materials can also be known as what term?
  • Question 157

    You are the HR Professional for your organization and you're working with the management to define the role of contractors versus employees in your organization.
    According to the Internal Revenue Service, there are three categories of control that help determine whether a person is a contractor or an employee. Which one of the following is not one of the three levels of control as defined by the IRS for employee versus contractor?
  • Question 158

    Which of the following should be the ClO's GREATEST consideration when making changes to the IT strategy'?
  • Question 159

    An enterprise is planning to migrate its IT infrastructure to a cloud-based solution but does not have experience with this technology Which of the following should be done FIRST to reduce the risk of IT service disruptions when using this new technology?
  • Question 160

    Which of the following frameworks defines ERM as the discipline by which an organization in any industry assesses, controls, exploits, finances, and monitors risks from all sources for the purpose of increasing the organization's short- and long-term value to its stakeholders?