Question 46
You want to create a reservation for a material component assigned to a network activity.
However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation?
Note: There are 2 correct answers to this question
                        
                    
                    However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation?
Note: There are 2 correct answers to this question
Question 47
You used hierarchical revenue planning to plan revenues for WBS elements manually. The cost element report for planned revenues does not show any revenues at all. What is the reason for this?
                        
                    
                    Question 48
Cost & Budget.
A customer wants to allocate overhead rates to a WBS element. What must you assign to the WBS element?
                        
                    
                    A customer wants to allocate overhead rates to a WBS element. What must you assign to the WBS element?
Question 49
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity.
What controls whether the delivery date is defined by the earliest or latest scheduled dates?
                        
                    
                    What controls whether the delivery date is defined by the earliest or latest scheduled dates?
Question 50
You want to determine the planned costs for an internally processed activity. Which data do you need?
Note: There are 2 correct Answers to this question.
                        
                    
                    Note: There are 2 correct Answers to this question.
 
            