Question 31

Wash-it-up is an organization that provides window cleaning services for the industrial sector. It has been certified t ISO 45001 for some time and has appointed a new OHS Manager. The audit plan during a surveillance audit includes the improvement actions and the auditor asks to see the most recent management review meeting minutes.
surveillance audit includes the Improvement actions and the auditor asks to see the most recent management review meeting minutes.
Which six of the statements would represent output audit evidence for the management review?
  • Question 32

    You are in the closing meeting of a second-party audit to ISO 45001. Which three of the following topics are most likely to come for discussion?
  • Question 33

    Select two of the following options which are not the responsibility of an audit team leader.
  • Question 34

    When calculating an ISO 45001 third party initial audit duration, which two of the following statements are false?
  • Question 35

    An audit team leader prepares the audit plan for an initial Stage 2 certification audit. Which two of the following statements are false?