Question 76

You need to create a purchase order for a thermal overload cooling fan for a refrigeration unit on the shop floor.
After creating a purchase order, what are the five steps, in sequence, for completing the order and receivingthe products? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Question 77

You are entering products and services into Dynamics 365 CE Field Services.
You need to ensure that your field technicians can use the products when completing work orders.
Which two field service product types should you configure to allow your technicians to add work order products? Each correct answer presents a complete solution.
  • Question 78

    You are setting your environment to use Resource Scheduling Optimization (RSO). You have enabled Optimize Schedule for all Bookable Resources.
    You need to complete the remaining steps to prepare your work order data for optimization.
    Which three actions should you perform, in sequence, to achieve the goal? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

    Question 79

    You are a Dynamics 365 for Field Service Administrator and work for a manufacturing firm. You are receiving support requests that field engineers are unable to see a custom area entitled "Parts Requests" within the Dynamics 365 Field Service Mobile App.
    You need to troubleshoot the Dynamics 365 for Field Service mobile app to ensure that the field engineers are able to view the customizations created.
    What are the three steps you can take to troubleshoot the issue reported? Each correct answer presents a complete solution.
  • Question 80

    DRAG DROP
    You are a Dynamics 365 for Field Service Dispatcher.
    You need to use the schedule board to find resources for a work order. The work order can be completed by any resource who has the correct piece of equipment and who is available at 9:00 A.M during a selected week.
    Which four steps must you take, in sequence, to successfully implement this capability within the schedule board? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
    Select and Place: