Question 216
A project team is mainly based in a metropolitan are
a. The team also has members in a remote area, where Internet access is limited and unstable.
Which of the following factors will MOST likely influence the communication methods used in the project?
a. The team also has members in a remote area, where Internet access is limited and unstable.
Which of the following factors will MOST likely influence the communication methods used in the project?
Question 217
A project team member has completed an assigned task on time.
After updating the project schedule, which of the following steps should the project manager take NEXT?
After updating the project schedule, which of the following steps should the project manager take NEXT?
Question 218
A customer has requested additional features for an active project.
Which of the following steps should take place NEXT?
Which of the following steps should take place NEXT?
Question 219
A project manager needs to identify the resources assigned to a particular task.
In which of the following documents can this information be found?
In which of the following documents can this information be found?
Question 220
A project manager is managing a project with a hard deadline in two weeks. At the current rate of progress, the project will not finish on time Which of the following techniques is
MOST likely to be used to complete the project on time?
MOST likely to be used to complete the project on time?