Question 226

A project manager has been assigned a complex project and does not know all the activities required to complete it.
Which of the following if the BEST approach to determine the work packages for the WBS?
  • Question 227

    A project manager is reviewing project performance. Which of the following would be the BEST indicator of the total project cost?
  • Question 228

    A project manager recently joined a projectized organization and is having many issues on five different projects. Which of the following risk activities should be performed FIRST? (Choose two.)
  • Question 229

    A meeting has taken place with quality assurance tram members and the project manager.
    Which of the following events would MOST likely have triggered the meeting?
  • Question 230

    A project manager needs to track the actual and estimated start and finish dates of all WBS work packages.
    Which of the following is a necessary step to record the actual durations?