Question 231

Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?
  • Question 232

    A company hires an outside vendor to provide 24/7 support.
    Which of the following documents would determine the contractual obligations?
  • Question 233

    Which of the following is the primary purpose of an MOA or an MOU?
  • Question 234

    A project manager does not have enough time to complete several tasks on a critical path.
    The budget is a low concern. Which of the following should be used to complete the tasks on time?
  • Question 235

    A project manager is not going to finish a project on time but cannot change the deadline or add more budget.
    Which of the following types of change would allow the project manager to finish the project successfully?