Question 141
Which of the following activities are associated with the closing phase of a project? (Select
TWO)
TWO)
Question 142
A company has dictated project scope changes but has stated that the original budget still applies. Which of the following will MOST likely be impacted by the changes?
Question 143
A vendor is unable to deliver an order by the specified date.
Which of the following should be the project manager's NEXT steps? (Choose two.)
Which of the following should be the project manager's NEXT steps? (Choose two.)
Question 144
There is a project in which the team can only meet once every three months. When the team does meet, no one can remember what was discussed and decided upon last time; thus, progress is being delayed. Which of the following project management tools would help?
Question 145
Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?