Question 171

A project coordinator logs potential events that can affect project constraints, and then records the results of brainstorming of potential strategies.
Which of the following documents should the project coordinator use?
  • Question 172

    The internal project sponsor is frustrated by a lack of concise, regular updates regarding the status of a project.

    Which of the following changes would BEST satisfy the project sponsor?
  • Question 173

    A project team is overseeing the installation of a new reptile habitat at the local zoo. During execution, zoo personnel decides to house a different type of reptile that will require a different temperature range than the capacity of the installed system. The modification has been approved.
    Which of the following constraints are MOST likely to be affected? (Choose two.)
  • Question 174

    A project manager has received a change order that will reduce a project's timeline and budget.
    However, the change order also indicates the goals and deliverables of the project must remain unchanged. Which of the following is the MOST logical impact to the project?
  • Question 175

    The upper management team does not agree with certain aspects of a project. Which of the following would be the BEST way for the project manager to handle this situation?