Question 161
A stakeholder does not want to receive tollgate approval emails, and asks the project manager to identify a different communication method. Which of the following would be BEST for the project manager to suggest?
Question 162
Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?
Question 163
A project's key stakeholders have requested significant changes that will affect the scope. To adjust the project scope, which of the following need to be changed? (Choose two.)
Question 164
Which of the following risk strategies prevents a risk from impacting a project?
Question 165
Based on the information below:
AC=100
SV=80
EV=120
Which of the following is the CPI of the project?
AC=100
SV=80
EV=120
Which of the following is the CPI of the project?