Question 161

A stakeholder does not want to receive tollgate approval emails, and asks the project manager to identify a different communication method. Which of the following would be BEST for the project manager to suggest?
  • Question 162

    Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?
  • Question 163

    A project's key stakeholders have requested significant changes that will affect the scope. To adjust the project scope, which of the following need to be changed? (Choose two.)
  • Question 164

    Which of the following risk strategies prevents a risk from impacting a project?
  • Question 165

    Based on the information below:
    AC=100
    SV=80
    EV=120
    Which of the following is the CPI of the project?