Question 191

A project manager is working on the project charter Which of the following phases does this describe?
  • Question 192

    A project manager in a function organization is resource leveling the upcoming phase. The project manager notices one of the resources is assigned with 20% of allocation to a secondary project. This situation limits and jeopardizes the commitment date.
    Which of the following should the project manager do NEXT?
  • Question 193

    A hurricane occurs in an area where several key project resources are located. When reviewing the project dashboard, the project sponsor sees the project is behind schedule and asks the project manager for an explanation. Which of the following documents should the project manager examine NEXT to provide an explanation?
  • Question 194

    A project team has just implemented an approved change to a project.
    Which of the following should occur NEXT?
  • Question 195

    Before a team can start on a sprint, they will need to: