Question 206

During the execution phase of a project, a project task has run longer than anticipated.

Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?
  • Question 207

    Halfway through a project, the project manager is told it needs to be completed four weeks earlier than originally planned. Which ot the following will MOST likely be impacted to accomplish this goal?
  • Question 208

    Upper management asks a project sponsor to provide several ad hoc reports as a brief overview of the project's current status.
    Which of the following types of reports should the project sponsor use to quickly summarize the status report data?
  • Question 209

    A project team added a new member who has proprietary information about a competitor's product. The team member was suddenly removed from the project. Which of the following MOST likely occurred?
  • Question 210

    A vendor was removed from a company due to non-performance but continues to submit invoices for work that was not completed. Which of the following should the project manager do to stop the vendor from sending invoices?