Question 206
During the execution phase of a project, a project task has run longer than anticipated.

Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?

Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?
Question 207
Halfway through a project, the project manager is told it needs to be completed four weeks earlier than originally planned. Which ot the following will MOST likely be impacted to accomplish this goal?
Question 208
Upper management asks a project sponsor to provide several ad hoc reports as a brief overview of the project's current status.
Which of the following types of reports should the project sponsor use to quickly summarize the status report data?
Which of the following types of reports should the project sponsor use to quickly summarize the status report data?
Question 209
A project team added a new member who has proprietary information about a competitor's product. The team member was suddenly removed from the project. Which of the following MOST likely occurred?
Question 210
A vendor was removed from a company due to non-performance but continues to submit invoices for work that was not completed. Which of the following should the project manager do to stop the vendor from sending invoices?