Question 101
Based on the burndown chart, what is the iteration's status?


Question 102
How does Empirical Process Control support Agile methodologies?
Question 103
A scrum team has conducted regular retrospectives to discuss immediate concerns and the implementation of improvement actions. Despite this, after a few iterations, the same concerns resurface.
What should the team have done to improve retrospective outcomes?
What should the team have done to improve retrospective outcomes?
Question 104
Which of the following is a list of capabilities, features, and stories that the Product Owner has identified?
Question 105
Assuming one-week iterations and a team of four developers, how many iterations will it take the team to complete a project with 27 story points if they have a velocity of 4?