Question 36
The following chart lists stories for a release of an Agile project:

If the velocity of the team is 10, how many iterations will be needed to complete all of the stories?

If the velocity of the team is 10, how many iterations will be needed to complete all of the stories?
Question 37
While reviewing the sprint burn down during a stand up. the scrum team identifies that they have fallen behind. Upon further discussion, they discover that some quality assurance (QA) team members were unable to use the new automation framework, which caused a bottleneck.
What should the scrum team do?
What should the scrum team do?
Question 38
Which of the following is NOT a characteristic of an Agile plan?
Question 39
A project team identifies a number of technical challenges with features in the next sprint.
What should they do?
What should they do?
Question 40
During a project's last few sprints, an agile practitioner notices an increase in defects. A root-cause analysis indicates that a poor understanding of the requirements was caused by the inability of the product owner to communicate clearly.
What should the agile practitioner do?
What should the agile practitioner do?