Question 81
A business analyst is working on a project to update the user interface for a legacy procurement system. An end user raises concerns that the new solution will not support their core business processes.
How could the business analyst address the end user's concerns about the new interface?
How could the business analyst address the end user's concerns about the new interface?
Question 82
A project's requirements baseline is established and approved. A stakeholder then submits a new requirement through the change control process.
How can the business analyst determine the impact on existing requirements?
How can the business analyst determine the impact on existing requirements?
Question 83
An organization is in the process of replacing its current system. The business analyst is charged with ensuring that all current connections to other systems remain functional after the upgrade.
What analysis should the business analyst conduct to facilitate a successful migration?
What analysis should the business analyst conduct to facilitate a successful migration?
Question 84
A business analyst created requirements for production of a product extract file for several systems. After reviewing the complex systems and dividing the processes into manageable tasks, the business analyst is able to identify the tasks required to implement the deliverable.
Which analysis technique has the business analyst used?
Which analysis technique has the business analyst used?
Question 85
A business analysl assigned lo review lest output for a project realizes that an approved requirement has been missed. Which technique could the business analyst have used to ensure that requirements were delivered as stated?