Question 1
Nancy is the project manager of the NHH project. She and the project team have identified a significant risk in the project during the qualitative risk analysis process. Bob is familiar with the technology that the risk is affecting and proposes to Nancy a solution to the risk event. Nancy tells Bob that she has noted his response, but the risk really needs to pass through the quantitative risk analysis process before creating responses. Bob disagrees and ensures Nancy that his response is most appropriate for the identified risk. Who is correct in this scenario?
Question 2
For the last several months, a project manager for a global technology program is focused on improving the project outsourcing process and analyzing the vendor supply chain as key pieces of the cost containment strategy. Early in the project, these two areas were identified as key risks to the final delivery of the project.
Since that initial risk identification, the risk manager works to identify additional risks, as well as analyze the potential impact to the project cost baseline. After performing a cost-risk sensitivity analysis, the risk manager produces this chart.

Based on this analysis, which two risk areas should the project manager focus on to control project cost?
Since that initial risk identification, the risk manager works to identify additional risks, as well as analyze the potential impact to the project cost baseline. After performing a cost-risk sensitivity analysis, the risk manager produces this chart.

Based on this analysis, which two risk areas should the project manager focus on to control project cost?
Question 3
You are the project manager of the BJA Project for your company. Management is worried about one of the identified risks in your project. The risk event has a probability of 90 percent and a cost impact of $85,000.
Management and you discuss possible solutions to address the risk. You share with them that for $75,000 you can reduce the probability of the risk event to 15 percent and the impact to $25,000. This solution will add three weeks to the project schedule. Management thinks this is a good idea and they would like you to add the time and cost additions to your project plan. What type of risk response is used?
Management and you discuss possible solutions to address the risk. You share with them that for $75,000 you can reduce the probability of the risk event to 15 percent and the impact to $25,000. This solution will add three weeks to the project schedule. Management thinks this is a good idea and they would like you to add the time and cost additions to your project plan. What type of risk response is used?
Question 4
There are seven risk responses, a project manager can use to address risk events. Which one of the following is a risk response that is appropriate for positive or negative risk events depending on the scenario in the project?
Question 5
The project manager schedules a third workshop to facilitate the qualitative risk analysis. One team member complains that they should not have iterative meetings, but rather, should complete this at the beginning of the project.
Which of the following should the project manager do?
Which of the following should the project manager do?