Question 6

A two-year project with a budget of US$2 million has completed about 60% of the work at the end of the first year. The actual cost incurred to complete the remaining 40% of work is about USS1.5 million. As a part of performing a specialized risk analysis, the calculated schedule performance index (SPI) is 1.2 and cost performance index (CPI) is 0.53.
How should the risk manager interpret such a low CPI value?
  • Question 7

    What best describes the job of a risk owner?
  • Question 8

    The project manager must evaluate two separate contractors for a project with an absolute finish date of 15 December. After performing a Monte Carlo assessment on the submitted schedules, the following information is found:

    Which contractor should be chosen, because of having the highest statistical output?
  • Question 9

    Ben is the project manager of the YHT Project for his company. Alice, one of his team members, is confused about when project risks will happen in the project. Which one of the following statements is the most accurate about when project risk happens?
  • Question 10

    You are the project manager of the AMD project for your organization. In this project, you are currently performing quantitative risk analysis. The tool and technique you are using is simulation where the project model is computed many times with the input values chosen at random for each iteration. The goal is to create a probability distribution from the iterations for the project schedule. What technique will you use with this simulation?