Question 66
Your project management office implemented a project management methodology that emphasizes the importance of integrated change control. It states that change requests can occur in all the following forms EXCEPT______________
Question 67
Inputs to quality planning include
Question 68
You are a project manager of ABC organization. You are estimating the project in initiation phase. What level of accuracy you can expect?
Question 69
You are a project manager tasked with a project of constructing six similar buildings in sequence. The project is estimated to cost $250,000 with a project timeline of four months. During a review after two months, you found that only two buildings are ready. The Actual Cost is $100,000. The project status is:
Question 70
Project risks have been identified through a brainstorming session While analyzing the risks, the project manager needs to quantify and prioritize the risks and develop the mitigation plan.
What should the project manager use?
What should the project manager use?