Question 76

Which of the following is NOT included in the project scope statement?
  • Question 77

    Complete final contract performance reporting and verify product is done in
    _______ .
  • Question 78

    Which theory(s) prescribes a form of participative management?
  • Question 79

    Which of the following is NOT a part of the preliminary scope statement?
  • Question 80

    Your organization discusses running a project which will entail an investment of $1,000,000. The product from the project is forecasted to create revenues of $250,000 in the first year after the end of the project and of $420,000 in each of the two following years.
    What is true for the Net present value of the project over the three years cycle at a Discount rate of 10%?