Question 91

A large corporation completed a corporate social responsibility project, and the project team has prepared the project's final report. As soon as the project ends, a TV reporter calls the project manager and asks to receive a copy of this report.
What should the project manager do first?
  • Question 92

    A Scrum Master comes to realize that the project team has grown exponentially over the course of several product releases. Due to this, communication is starting to become a major challenge.
    What should the Scrum Master do?
  • Question 93

    You are the project manager. Which of the following would be required to ascertain what impact a change would have on the project in a situation where a customer requests a scope change in the project? Note: you already have the work breakdown structure, change request and scope management plan.
  • Question 94

    Project management processes ensure the:
  • Question 95

    What are assigned risk ratings based upon?