Question 156

The table lists project activities, with activities A and H as start and end activities.
What is the project's critical path?
  • Question 157

    Ono week after project deployment, a project manager unsuccessfully tries to resolve an issue on then own.
    The project manager failed to inform stakeholders, which results in their frustration.
    To avoid stakeholder frustration, what should the project manager have done?
  • Question 158

    You finally have been appointed project manager for a major company project. One of your first activities as project manager will be to create the communications management plan. As you match the stakeholder with the appropriate communication methods for that stakeholder, you could use any one of the following methods EXCEPT______________
  • Question 159

    Drag the communication event on the left to the main subject discussed during the event on the right.

    Question 160

    Your organization is characterized by hierarchical organizational structures with rigid rules and policies and strict supervisory controls. Individual team members are not expected to engage in problem solving or use creative approaches to plan and execute work; management does that. Your organization is characterized by which one of the following theories?