Question 166
The cost performance baseline is typically displayed in the form of:
Question 167
Perform Quality Control is accomplished by:
Question 168
Which of the following are outputs of Develop Project Team?
Question 169
Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?
Question 170
You are the project manager responsible for renovating a 70-year old building. You intend to hire an outside construction firm to seismic retrofit the building in order to make sure that the building can withstand the large earthquakes. You are in process of selecting a contract type best suited for this project. You would like to select a contract type that transfers the risk onto the seller for any cost risks and no-performance issues. Which contract type should you choose?