Question 971
A company is merging with another company, and some employees have already been asked to leave, A project team, working on delivering critical projects for all key company products, is unmotivated because members fee! they may be asked to leave next.
What should the project manager do to motivate the team to stay focused on the projects during the merger?
What should the project manager do to motivate the team to stay focused on the projects during the merger?
Question 972
At a recent steering committee meeting, the project sponsor asked the project team to add a major feature to the final product. After consulting with the project team, it is determined that the change will cause significant impacts to the original project delivery date and budget.
What should the project manager do to assess the priorities and meet the new objective?
What should the project manager do to assess the priorities and meet the new objective?
Question 973
As a project is reaching completion, the project sponsor tells the project manager to immediately close the project and to move on to another project. Which critical task should the project manager complete before closing the project?
Question 974
A company that is introducing a new product into the market by the end of the year requires a storage and distribution facility to be built. During the monthly stakeholder meeting, it is discovered that the location for implementation is a government-owned area What should the project manager do first?
Question 975
Which project risk listed in the table below is most likely to occur?