Question 91
A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?
Question 92
A sponsor and project manager found out that a vendor in a different time zone has delayed the delivery of its products and needs close supervision until the project gets back on track. The only option is to relocate three key members of the project team to spend 6 months abroad What should the project manager do next?
Question 93
You are a senior project manager and member of the Project Management Office. The CIO wants you to present a snapshot of the status of various projects going on in the organization. Which of the following charts would be most suitable for the purpose?
Question 94
As a result of the control stakeholder expectations process, you realize even though this process is under way until the closing phase that you have identified the root cause of some issues you have faced in controlling stakeholders expectations. You should therefore______________
Question 95
After reviewing an approved project's resource management plan, the project manager identifies that the proper resources were not assigned. What should the project manager do?