Question 116
Please refer to the chart given below, which shows the time estimates for different tasks:

What is the impact on the project if task 1->2 takes 2 months more than what was earlier planned? (Choose best answer)

What is the impact on the project if task 1->2 takes 2 months more than what was earlier planned? (Choose best answer)
Question 117
During a project to develop a new pharmaceutical product, the project manager was informed that there has been a change in government regulations regarding the materials of the project.
What should the project manager do?
What should the project manager do?
Question 118
A project manager is leading a hybrid project that is building an app for a travel industry startup. Due to unforeseen events, the features and the overall solution will not be useable by many customers due to new travel restrictions.
What should the project manager do first?
What should the project manager do first?
Question 119
The programming activities of a project were planned to last 35 days per module but the programming of the first module has taken 45 days What should the project manager do?
Question 120
The activity list should include descriptions of activities. This is required to:

Answer: B. The duration of the project will increase by 2 months
Explanation
The critical path is the longest sequence of dependent tasks from the start to the finish of a project, determining the shortest possible project duration.
Tasks on the critical path have zero float (or slack). Any delay in a critical task will cause the entire project to be delayed by an equal amount of time.
The provided table lists Earned Value Management (EVM) data (Planned Value, Actual Cost, Earned Value) which helps track performance against a baseline, but does not provide the task dependencies or durations needed to calculate the critical path directly.
The question assumes that the task 1->2 is a critical task. Therefore, a two-month delay in this task directly increases the project's overall duration by two months.