Question 436

A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:
  • Question 437

    At a project status meeting, different activities were agreed upon for the following weeks. At the end of the first week, the project team realizes that the activities were executed in the wrong way because each team member had a different understanding. These misunderstandings have caused a delay in the project.
    Which of the following actions should the project manager take to avoid this situation in the future?
  • Question 438

    You are using three point estimating technique to estimate the estimate of a scheduled activity. Which of the following statement are true given the following data:
    [Pessimistic=100 days] [Optimistic=40 days] [Most likely=65 days]Assuming a beta distribution you calculate that the duration average=66.6 days and duration variance=100.Assuming a triangular distribution you calculate that the duration average=68.33 days, and duration variance=151.38
  • Question 439

    Which of the following conflict resolution techniques describes a situation where each of the parties involved in the conflict give up something in order to reach a solution?
  • Question 440

    A regulation is a document that lays down provisions with which compliance is mandatory.