Question 211

Who does the Team Manager report to and take direction from?
  • Question 212

    According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?
  • Question 213

    Which of the following statements about lines of authority and reporting are true?
    1, The Project Manager has day-to-day control for a management stage within the limits laid,
    2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.
  • Question 214

    Which is a purpose of the Risk theme?
  • Question 215

    Which is a purpose of an End Project Report?